“…It seems this project has moved along well so far…” Just what does that mean and was there more to this e-mail?
Where is the certified performance test showing the boiler system works within design limits? What are the emissions discharged when the boilers fire?
Are all the installation drawings, service, and maintenance manuals turned over to the town for use in operating and maintaining the boilers? Where municipal departments assigned responsibilities for the equipment familiarized and trained on this equipment by the installing authority?
So, has it moved along well so far or does "so far" mean a number of incidentals like drawings, manuals and training got left out - - -?
Arre there financial penalties against WB for going beyond the completion date?
ReplyDeleteWhat date will it be done?
Altieri doesn't have a clue as to how this town should operate.
“…It seems this project has moved along well so far…” Just what does that mean and was there more to this e-mail?
ReplyDeleteWhere is the certified performance test showing the boiler system works within design limits? What are the emissions discharged when the boilers fire?
Are all the installation drawings, service, and maintenance manuals turned over to the town for use in operating and maintaining the boilers? Where municipal departments assigned responsibilities for the equipment familiarized and trained on this equipment by the installing authority?
So, has it moved along well so far or does "so far" mean a number of incidentals like drawings, manuals and training got left out - - -?
It's the close of business on September 30th, and it's STILL not done.
ReplyDeleteNow what?
Let's send it out to bid again.